In late September, a Post and Courier photographer walked the strip of old rail bed under Interstate 26 and found pallets of construction materials stacked behind fencing and a puddle across the path near Romney Street. Ground had been broken nine months earlier, on December 15, 2025, behind The Daily Café. To most people passing by, the corridor still looked like it had before.
That has changed. In October, WCIV reported, crews began excavating the soil along the 1.6-mile stretch from Mount Pleasant Street to Line Street and replacing it with clean, sandy fill. A city spokesperson told the Post and Courier that this is when the public would begin seeing "a much more obvious physical transformation of the corridor."
Most of what will surround the Lowline is arriving before the park. A hotel is already open on the corridor, a medical school building is due in late 2027, and an affordable apartment project has started building. The park comes last, in early 2028. For anyone buying a home near it, all of 2027 is a year of construction fencing, and the county market has cooled at the same time. That stretch is when a buyer has the most room to set terms.
The corridor's neighbors got there first
The Lowline Hotel at 560 King Street opened on July 15, 2026, according to Hotel Dive. Highline Hospitality Partners bought the former Hyatt Place in November 2024 and reopened it with 197 rooms. When it announced the reopening, WCIV reported that the hotel was built around immediate access to the park. Its Leeward Restaurant and Lowline Spirited Coffee opened with it. The hotel opened about a year and a half before the park it shares a name with.
A few blocks away, the same summer brought KYN to 61 Cannon Street and Two Blokes Brewing to 114 Cannon Street in August 2026, and Luther's Market + Noodle Shop to 227 Rutledge Avenue in June, per Explore Charleston's October list of openings.
Housing is moving too. Lowline Apartments is a five-story, 55-unit affordable rental project next to the corridor near King Street. In November, Lowline Housing LP asked Charleston County for a $396,000 incentive, and Live 5 reported that construction on the first phase had already started.
The biggest anchor is MUSC's. The university's new 186,000-square-foot College of Medicine building topped out in August and is scheduled to open in late 2027, letting the medical school's class grow from 180 to 220 students, Live 5 reported. Farther out, the Post and Courier reports a $1.115 billion, 600,000-square-foot Hollings cancer hospital near Calhoun Street, projected to open in April 2030.
The proposals that show where builders are looking
Behind what's already open or under construction is a list of plans that haven't broken ground. The Post and Courier has reported a proposed 150-room Montford Hotel at 245 Huger Street from developer Sunju Patel and a proposed 191-room Thompson by Hyatt where Meeting Street meets Morrison Drive, from TMGOC Ventures. At 1300 Meeting Street, the paper reported, Morrison OZB LLC has proposed a 149-room hotel with 13 condos, retail space and a restaurant. Its rezoning application was deferred for more review.
Near MUSC, the Post and Courier has also reported a proposed 62-acre, 61-parcel Medical District that would support the institution's Calhoun Street innovation district. None of these projects has broken ground yet. Taken together, they show developers lining up along this corridor before the park opens. For a buyer, a proposal on the next parcel is part of what a home will sit beside in a few years, and our entitlement and development consulting work follows proposals like these for that reason.
The park itself arrives last, and in order
The schedule has slipped once already. The Post and Courier reported that the city approved more money because the Lowline's stormwater design had "changed drastically" since design work began in April 2025. This was the fifth change to the contract with Edifice Construction LLC, which now totals more than $10.3 million, and the project is expected to cost more than $20 million overall. The first phase was supposed to reach substantial completion in February. That target is now August 2027.
WCIV's November update set out the order of work. Construction will take about 21 months and move along the corridor from north to south. The earthwork phase is expected to wrap up in August 2027. A second phase covering the sidewall, plantings, lighting and site furnishings is targeted to start in May 2027 and finish in December, running from Mount Pleasant Street down to Sheppard Street. The city expects the park to open between Sheppard and Mount Pleasant streets in early 2028. WCIV reported that the third phase, at Bradford Park with a public restroom building, is not funded at this time.
The finished park will have separate walking and biking paths divided by planted medians, better lighting and safer street crossings. Parking is already in place. The city's July 2025 parking-management solicitation lists the Huger Street North, Huger Street South and Sheppard Street South lots, with a total capacity of 144 surface spaces. Friends of the Lowline, the nonprofit that has pushed for the project since 2012, describes the finished park as a car-free corridor linking North Central at one end to Radcliffborough at the other.
The order of work matters for a home search. Earthwork started at the north end, and the section between Mount Pleasant and Sheppard streets is the part scheduled to open first. A buyer near that section is looking at about a year of construction before a finished park, which is a shorter wait than for blocks farther south.
What the market is doing while the fences are up
The construction year lines up with a cooling market. The Charleston County median home price was $725,000 as of October 31, 2026, down from $770,000 the previous October, according to Charleston Trident Association of Realtors data reported by the Post and Courier. The paper also reported that October contracts were down 17 percent from October 2025, per the Charleston MLS, and quoted a local broker saying the market "hit the brakes" when mortgage rates went above 7 percent in September. Rates have stayed there. Freddie Mac's 30-year fixed average was 7.28 percent for the week of November 19, 2026, up from 6.26 percent a year earlier.
The upper peninsula looks even quieter. October 2026 MLS figures for the Upper Charleston Peninsula area showed eight closed sales, a $782,500 median, and an average of 74 days on market, up from 23 days in October 2025. Eight sales is too few for the median to mean much. One or two large closings either way would move it, which is the same small-sample problem we wrote about in Daniel Island's condo numbers. Days on market is a more dependable measure here. It tracks how long each seller waited, and in October 2026 upper-peninsula sellers waited roughly three times as long as they did a year earlier.
Put those numbers next to the construction calendar. Right now, a seller listing near the corridor faces mortgage rates above 7 percent, fewer contracts countywide than a year ago, and fenced earthwork down the street. Earthwork is scheduled to continue into August 2027, and the park buyers will be picturing won't open before early 2028. As long as those conditions hold, the seller is in a weaker position and a buyer who can live with the construction is in a better one.
Questions to settle before you write an offer
Start with how far the home is from the corridor and which section of the schedule that falls in. A home near the Mount Pleasant Street end will see earthwork first and the finished park first. A home near Line Street or Bradford Park is looking at a longer and less certain timeline.
Then walk the route. Construction fencing, the Sheppard Street South lot and the fill work along the old rail bed are all visible now. How the block feels on a weekday afternoon in December will tell you more about life during construction than any marketing description will.
Then look at what is proposed nearby. A home that backs onto a parcel tied to a deferred rezoning, like 1300 Meeting Street, has a different future than one next to a building that is already finished. For investors and small builders, the same list shows where hotel and institutional money expects people to be once the park opens.
Finally, price the waiting period. When average days on market roughly triples in a year, a buyer has room to ask for time, repairs or price, and a seller who wants to close before spring has reason to listen.
If you're weighing a home near the Lowline or a project along the corridor, talk it through with PRL Consulting Group before you write an offer or file a plan. Request a Market Valuation or Project Consultation, and bring the address and where it sits on the Lowline schedule.